Defense contractapprovedSeptember 01, 2026
Anniston Army Depot
FORGE depot modernization program launches
The U.S. Army launched a five-year modernization effort at Anniston Army Depot backed by a $986.97 million facilities award to Brasfield & Gorrie and an initial $658.17 million obligation.
The FORGE program combines four military-construction projects and 19 repair and maintenance projects to modernize the Alabama depot. The Mission and Installation Contracting Command oversees procurement, and the Army also awarded a separate $60.1 million architect-engineer contract to GM Hill-Baker JV for design, project management, and quality assurance.
Headline metrics
| Facilities award | $986.97M | |
| Initial obligation | $658.17M | |
| Project portfolio | 23 projects | 4 MILCON and 19 repair-and-maintenance projects |
Highlights
- Kickoff completeArmy and industry teams began the FORGE effort at Anniston on September 1.
- Organic industrial baseThe program is intended to turn a maintenance-focused depot into a more modern industrial enterprise.
- Design supportA separate $60.1 million contract covers technical design, project management, and quality assurance.
Resources
- U.S. Army FORGE kickoff reportarmy.mil