← Back to release log
Factory openingapprovedNovember 11, 2026
Modine

Airedale Grand Prairie chiller manufacturing facility begins commercial production

Modine commenced commercial production of Airedale 2 MW and 3 MW chillers at a new 682,000-square-foot advanced manufacturing facility in Grand Prairie, Texas, with its first production line operating.

The new Grand Prairie plant is dedicated to large chillers for high-density data-center cooling. Modine says the first line began operations in November and the facility currently runs one shift. Its target of four operating 2 MW production lines by fiscal year-end and a future three-shift model remain forward-looking and are not presented as completed capacity.

Headline metrics

Facility size682,000 square feetPurpose-built Grand Prairie manufacturing site
Products in production2 MW and 3 MW chillersAiredale chillers with free cooling
Operating lines1First production line began operations in November; four lines are only a target

Highlights

Resources